Day 9, 10 progress

It's coming together.  When I got there this evening the plumbing was in, basement floor prepped for concrete and backfill nearly complete.  Concrete is not far behind...

 I was hoping to get pictures of the plumbing before they covered it up, but I can't complain about progress!

I selected the three piece bathroom rough-in option but I was never told exactly what to be expecting.  Somehow this does not look complete:

On the floorplan, the shower is supposed to be along the wall on the right of the picture with the toilet and sink along the other wall.  I didn't get a better picture, but I didn't see a drain setup for the shower.

all ready for concrete