Tuesday, April 9, 2013

Day 8 - waterproofing and some backfill

Today's progress: waterproofing, which comes up way higher than I thought, and most of the backfill. I also saw the plumbing supplies were delivered - hopefully to be installed tomorrow :)

One of the things I noticed was all of the trash and debris; such a mess...  There was quite a bit around the base of the foundation on the outside as well as inside the basement.  I bet this stuff will just be buried by the backfill...

 
standing in the garage
back view (unfortunately standing way beyond property line)
down the welled exit, quite a few more steps down than I had imagined
front corner not yet backfilled


construction mess at the base of foundation - to be buried

plumbing supplies!