Timeline

January
1/6/2013 - Signed Contract
1/11/2013 - Meeting with NVR Mortgage
1/17/2013 - CTI and M&R Floors
1/21/2013 - Guardian meeting
1/26/2013 - Option finalization (well, mostly final:)) w/SR

February
2/1/2013 - Found lot was staked
2/4/2013 - Pre-construction meeting
2/5/2013 - NVR approval
2/25/2013 - Estimate for construction start! - OK, didn't happen due to permit

March
3/5/2013 - Building permit approved (finally - they received it on 1/23)
Can we begin now???  I guess not.  Needless to say the month of March was very long.

April
4/2/2013 - CONSTRUCTION START - we have a hole!
4/4  - 4/9 - digging, footers, basement wall, waterproofing, partial backfill
4/15 - basement and garage concrete poured
4/17 - framing first floor
4/18 - framing second floor
4/19 - roof and basement interior walls
4/22, 4/23 - windows and doors and stairs
4/24, 4/25 - roofing, house wrap and low-e silver "space suit" (additional reflective insulation/wrap), garage door